According to the schedule, how many days are required to complete the project?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

According to the schedule, how many days are required to complete the project?

Explanation:
The time to complete the project is governed by the longest chain of dependent activities, the critical path. The schedule’s total duration equals the sum of the durations along that path, and any delay on that path pushes the project finish date. If the schedule shows the final milestone landing at day 28, that means the critical path requires 28 days, so the project can’t be completed in fewer days. Slack on non-critical paths won’t shorten the overall duration because those paths aren’t the limiting factor. Remember to align the counted days with the calendar being used (calendar days versus workdays) as shown in the schedule. In this case, the indicated finish is 28 days, so that’s the required completion time.

The time to complete the project is governed by the longest chain of dependent activities, the critical path. The schedule’s total duration equals the sum of the durations along that path, and any delay on that path pushes the project finish date. If the schedule shows the final milestone landing at day 28, that means the critical path requires 28 days, so the project can’t be completed in fewer days. Slack on non-critical paths won’t shorten the overall duration because those paths aren’t the limiting factor. Remember to align the counted days with the calendar being used (calendar days versus workdays) as shown in the schedule. In this case, the indicated finish is 28 days, so that’s the required completion time.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy