If 30 gates are scheduled to be delivered sequentially over 24 months, the planned rate is 1.25 gates per month. After 11 months, approximately how many gates should be operational?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

If 30 gates are scheduled to be delivered sequentially over 24 months, the planned rate is 1.25 gates per month. After 11 months, approximately how many gates should be operational?

Explanation:
With a steady, planned delivery, the number of gates completed grows linearly with time. The rate is the total gates divided by the total months: 30 gates / 24 months = 1.25 gates per month. After 11 months, the expected completed gates are 1.25 × 11 = 13.75. So, about 13.75 gates should be operational. (If rounding to whole gates, this would be about 14.)

With a steady, planned delivery, the number of gates completed grows linearly with time. The rate is the total gates divided by the total months: 30 gates / 24 months = 1.25 gates per month. After 11 months, the expected completed gates are 1.25 × 11 = 13.75. So, about 13.75 gates should be operational. (If rounding to whole gates, this would be about 14.)