In CPFF contract pricing, which statement is true?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

In CPFF contract pricing, which statement is true?

Explanation:
In CPFF pricing, the contractor is paid for allowable costs incurred to perform the work, plus a fixed fee that does not vary with actual costs. This combination—reimbursed costs plus a fixed, predetermined fee—defines the arrangement and distinguishes it from fixed-price contracts, where the price is set upfront and not tied to the contractor’s costs. While many CPFF agreements include a ceiling (not-to-exceed) price to cap total reimbursement, the essential concept you’re testing is that costs are reimbursed and a fixed fee is added. The other statements don’t fit: a CPFF contract is not fixed-price, and there is inherent risk to the buyer because costs can rise up to the ceiling; the presence of a ceiling price is a separate feature, not the defining pricing mechanism.

In CPFF pricing, the contractor is paid for allowable costs incurred to perform the work, plus a fixed fee that does not vary with actual costs. This combination—reimbursed costs plus a fixed, predetermined fee—defines the arrangement and distinguishes it from fixed-price contracts, where the price is set upfront and not tied to the contractor’s costs. While many CPFF agreements include a ceiling (not-to-exceed) price to cap total reimbursement, the essential concept you’re testing is that costs are reimbursed and a fixed fee is added. The other statements don’t fit: a CPFF contract is not fixed-price, and there is inherent risk to the buyer because costs can rise up to the ceiling; the presence of a ceiling price is a separate feature, not the defining pricing mechanism.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy