PV = $190,000, EV = $150,000, AC = $170,000. What does this indicate about SV and CV?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

PV = $190,000, EV = $150,000, AC = $170,000. What does this indicate about SV and CV?

Explanation:
In earned value terms, schedule variance (SV) shows whether the work completed is ahead or behind plan, and cost variance (CV) shows whether spending is under or over budget. SV is calculated as EV minus PV, and CV as EV minus AC. Here, planned value (PV) is 190,000, earned value (EV) is 150,000, and actual cost (AC) is 170,000. SV = 150,000 − 190,000 = −40,000, which is negative, so the project is behind schedule by 40,000 of planned value. CV = 150,000 − 170,000 = −20,000, which is negative, so the project is over budget by 20,000. Therefore, the project is behind schedule and over budget.

In earned value terms, schedule variance (SV) shows whether the work completed is ahead or behind plan, and cost variance (CV) shows whether spending is under or over budget. SV is calculated as EV minus PV, and CV as EV minus AC.

Here, planned value (PV) is 190,000, earned value (EV) is 150,000, and actual cost (AC) is 170,000. SV = 150,000 − 190,000 = −40,000, which is negative, so the project is behind schedule by 40,000 of planned value. CV = 150,000 − 170,000 = −20,000, which is negative, so the project is over budget by 20,000.

Therefore, the project is behind schedule and over budget.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy