What is the total float of activities AC-D?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

What is the total float of activities AC-D?

Explanation:
Total float is the amount of time an activity can be delayed without delaying the project finish. It’s found by comparing the activity’s earliest timing with its latest timing: total float = latest start minus earliest start (or latest finish minus earliest finish). To determine it, you compute ES and EF through a forward pass, then LS and LF through a backward pass from the project deadline. The difference for this activity comes out to four days, so AC-D can be delayed by up to four days without pushing the project end date back. This also means AC-D is not on the critical path. For example, if AC-D has ES = 6 and duration 4 (EF = 10), and LS = 10 and LF = 14, then total float = LS − ES = 4 days.

Total float is the amount of time an activity can be delayed without delaying the project finish. It’s found by comparing the activity’s earliest timing with its latest timing: total float = latest start minus earliest start (or latest finish minus earliest finish).

To determine it, you compute ES and EF through a forward pass, then LS and LF through a backward pass from the project deadline. The difference for this activity comes out to four days, so AC-D can be delayed by up to four days without pushing the project end date back. This also means AC-D is not on the critical path. For example, if AC-D has ES = 6 and duration 4 (EF = 10), and LS = 10 and LF = 14, then total float = LS − ES = 4 days.