What term describes the amount of time an activity can be delayed without delaying the early start date?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

What term describes the amount of time an activity can be delayed without delaying the early start date?

Explanation:
Free float is the amount of time an activity can be delayed without delaying the early start date of its successors. This means you can push that activity back by that many days and still have all immediate following tasks begin as planned on their earliest dates. It’s different from total float, which is the amount of delay that can occur without affecting the project’s finish date. For example, if an activity finishes on day 5 and its successor must start by day 7, you could delay the activity by up to 2 days without delaying the successors, which is free float. Delaying beyond that would push the successors and potentially the project finish, relating to total float instead.

Free float is the amount of time an activity can be delayed without delaying the early start date of its successors. This means you can push that activity back by that many days and still have all immediate following tasks begin as planned on their earliest dates. It’s different from total float, which is the amount of delay that can occur without affecting the project’s finish date. For example, if an activity finishes on day 5 and its successor must start by day 7, you could delay the activity by up to 2 days without delaying the successors, which is free float. Delaying beyond that would push the successors and potentially the project finish, relating to total float instead.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy