Which float measures the total time an activity can be delayed without delaying the project finish date?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

Which float measures the total time an activity can be delayed without delaying the project finish date?

Explanation:
Total float is the amount of time an activity can be delayed without delaying the project finish date. It reflects scheduling flexibility across the whole project, not just in relation to a single successor. You compute it as the difference between the latest finish time and the earliest finish time (or latest start minus earliest start) for that activity. If total float is positive, you can delay the activity by that amount without affecting the project end; if it’s zero, the activity is on the critical path and any delay would push the finish date. This is different from free float, which is the time you can delay an activity without delaying the start of its immediate successors. Therefore, the measure described is total float.

Total float is the amount of time an activity can be delayed without delaying the project finish date. It reflects scheduling flexibility across the whole project, not just in relation to a single successor. You compute it as the difference between the latest finish time and the earliest finish time (or latest start minus earliest start) for that activity. If total float is positive, you can delay the activity by that amount without affecting the project end; if it’s zero, the activity is on the critical path and any delay would push the finish date. This is different from free float, which is the time you can delay an activity without delaying the start of its immediate successors. Therefore, the measure described is total float.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy