Which pair represents two common CPM network diagram types used in construction scheduling?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

Which pair represents two common CPM network diagram types used in construction scheduling?

Explanation:
This question tests recognizing the two common CPM network diagram styles used in construction scheduling. The Arrow Diagramming Method shows activities as arrows and events as points, with durations attached to the arrows and the network flowing from one event to another. The Precedence Diagramming Method is the modern standard, representing activities as nodes (boxes) and using directed connections to show dependencies, including finish-to-start, start-to-start, finish-to-finish, and start-to-finish relationships. Together they form the two widely used CPM diagram families in practice. Other pairings mix a diagram style with the scheduling method or pair closely related concepts, whereas ADM and PDM are the best-known, distinct diagram types used for CPM in construction.

This question tests recognizing the two common CPM network diagram styles used in construction scheduling. The Arrow Diagramming Method shows activities as arrows and events as points, with durations attached to the arrows and the network flowing from one event to another. The Precedence Diagramming Method is the modern standard, representing activities as nodes (boxes) and using directed connections to show dependencies, including finish-to-start, start-to-start, finish-to-finish, and start-to-finish relationships. Together they form the two widely used CPM diagram families in practice. Other pairings mix a diagram style with the scheduling method or pair closely related concepts, whereas ADM and PDM are the best-known, distinct diagram types used for CPM in construction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy