Which statement describes the traditional delivery system's major phases being executed in a linear sequence?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

Which statement describes the traditional delivery system's major phases being executed in a linear sequence?

Explanation:
The traditional delivery system relies on a linear progression where each major phase follows the previous one in a fixed order. In design-bid-build, the design is completed and documented before any construction starts, and a contractor is brought in based on those finalized plans. Construction then proceeds after the design is locked, with little or no overlap between design and construction activities. This sequential flow is what defines the method. If phases were simultaneous, you’d be describing fast-tracking or an integrated design-build approach, not the traditional method. Describing it as random wouldn’t fit, since the process is intentionally structured in a set order.

The traditional delivery system relies on a linear progression where each major phase follows the previous one in a fixed order. In design-bid-build, the design is completed and documented before any construction starts, and a contractor is brought in based on those finalized plans. Construction then proceeds after the design is locked, with little or no overlap between design and construction activities. This sequential flow is what defines the method. If phases were simultaneous, you’d be describing fast-tracking or an integrated design-build approach, not the traditional method. Describing it as random wouldn’t fit, since the process is intentionally structured in a set order.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy