Who is typically required to prepare and submit a recovery plan when delays are contractor-caused?

Become proficient in Construction Management. Study with flashcards and multiple choice questions, each question is detailed with hints and explanations. Excel in your exam!

Multiple Choice

Who is typically required to prepare and submit a recovery plan when delays are contractor-caused?

Explanation:
When delays are caused by the contractor, the party responsible for executing the work must propose how to recover. The contractor controls the methods, resources, and sequencing of activities, so they are in the best position to develop a plan to bring the project back on track. A recovery plan outlines concrete actions—adding crews or overtime, re-sequencing work, fast-tracking activities, or other acceleration measures—and shows the impact on milestones and the new completion date. While the owner and the construction manager review and approve the plan and monitor its implementation, the obligation to prepare and submit it rests with the contractor because only they can implement the changes necessary to recover the schedule.

When delays are caused by the contractor, the party responsible for executing the work must propose how to recover. The contractor controls the methods, resources, and sequencing of activities, so they are in the best position to develop a plan to bring the project back on track. A recovery plan outlines concrete actions—adding crews or overtime, re-sequencing work, fast-tracking activities, or other acceleration measures—and shows the impact on milestones and the new completion date. While the owner and the construction manager review and approve the plan and monitor its implementation, the obligation to prepare and submit it rests with the contractor because only they can implement the changes necessary to recover the schedule.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy